Bonjour,
26 hours after a vCenter Appliance upgrade from 6.0 to 6.0 update 2, the vCenter started a complete SDRS storage vMotion for all machines (1164) in all data store clusters. the process was active for 12 hours and was finally completed.
As SDRS uses a 24 hours calculation period:
Question:
1- After an update, do you clear the SDRS calculation/Database?
2- Are there any changes in the vCenter on SDRS calculation method in the update 2?
3- Do we have to expect a complete storage DRS re-organisation after a vCenter upgrade?
Thanks and best regards.